WHITESANDS Project

Whitesands

The WHITESANDS project design was engineered in 2003 and consists of three horizontal wells (500 metres long and 100 metres apart), three vertical air injection wells and 19 vertical observation wells (17 for temperature and two for pressure observations). Petrobank received approval for the project in 2004 and construction commenced in 2005.

Start-up of the WHITESANDS project began in late March of 2006 with the initiation of the PIHC (Pre-Ignition Heating Cycle) in the central well pair. Air injection and combustion were initiated in mid-July 2006 and by year end, production had ramped up considerably, with gross production capability from the first horizontal well of up to 2,000 barrels of fluid per day, approximately double our initial forecast rate, with oil cuts currently between 40 and 50 percent.

Read more about THAI™ Technology.

Click here for information on the May River Project.



 
 
Whitesands Expansion Application WHITESANDS Project Expansion Application
Download PDF (8.5 MB)
PDF
Whitesands Application EUB Application
Download PDF (38 MB)
PDF

Supplemental Information Requests and Responses

EUB/AENV Supplemental Information Requests and Responses
Download PDF (2.54 MB)
PDF
 
Map 1 Map 1
Conklin Region Infrastructure and Industrial
Development
Download PDF (0.2 MB)
PDF
 
Map 2 Map 2
Infrastructure in the Vicinity of the WHITESANDS
Project
Download PDF (0.5 MB)
PDF
Mouse-over to enlarge